List of All CPEC Projects in Pakistan

Sindh

Port Qasim Electric Company Coal Fired

  • Work Started: May 2015
  • Completion: Approximately 65% Power Plant and 70% Jetty completed
  • Energization: October 2017
  • Commercial Operation Date: June 2018
Also read: CPEC lifts Pakistan’s ranking in the world

 Surface mine in Block II of Thar Coalfield, Thar Sindh

  • Financial Close (FC) achieved
  • COD expected 2018/2019

SSRL Thar Coal Block 1 Thar

  • Commercial Operation Date (COD) expected 2018 / 2019
  • SSRL 2×660 MW Mine Mouth Power Plant, Sindh
  • Expected Commercial Operation Date (COD) 2018 / 2019

Dawood 50MW wind Farm, Bhambore

  • Financial Close (FC) achieved
  • Construction started.
  • Commercial Operation Date (COD) Jan 2017

Karachi Circular Railway

  • JCC agreed in principle for inclusion of Rail Based Mass Transit Systems in Provincial headquarters as part of CPEC
  • JWG on Transport Infrastructure has been asked to complete the necessary formalities

Pakistan Wind Farm II 2X50 MW(Jhampir, Thatta, Sindh)

  • LOS issued in August 2016
  • Construction activity already started from equity.
  • COD Sep 2018

 Thar mine mouth oracle, Thar Sindh

  • Feasibility stage tariff obtained for coal.
  • Shareholding agreement on new equity partners in process

 UEP 100MW wind Farm, Jhimpir, Sindh

  • Construction started.
  • Sub-station under construction, to be completed by March 2017
  • Commercial Operation Date (COD) Expected June 2017

 Sachal 50MW Wind Farm, Jhimpir

  • Construction in progress.
  • Commercial Operation Date (COD) June 2017
Must read: CPEC is hiring in Pakistan

Baluchistan

Gwadar Coal-fired Power Project, Gwadar

  • CCCC has registered with PPIB
  • Work initiated

HUBCO coal power plant

  • IA/EA Signed
  • Commercial Operation Date (COD) expected 2018/2019

Engro Thar  Coal-fired, Thar

  • Financial Close (FC) achieved: April 2016
  • Team mobilized at site
  • Construction work in progress
  • Commercial Operation Date (COD) June 2019

Gaddani Power Park Project (Jetty + Infrastructure)

  • Under Study

HUBCO coal power plant 1X660 MW, Hub Balochistan

  • IA/EA Signed
  • . COD expected 2018/2019

 Gaddani Power Park Project (2×660MW)

  • Under Study

 Gwadar East-Bay Expressway

  • Minutes of EAD-MOFCOM signed

New Gwadar International Airport

  • Minutes of EAD-MOFCOM signed in August 2016
  • Grant request is being processed by Chinese Side

 Technical and Vocational Institute at Gwadar

  • Chinese technical team expected to visit early this year to conduct feasibility study
  • MoU likely to be signed soon

 Quetta Mass Transit

  • JCC agreed in principle for inclusion of Rail Based Mass Transit Systems in Provincial headquarters as part of CPEC
  • JWG on Transport Infrastructure has been asked to complete the necessary formalities

Quetta Water Supply Scheme from Pat Feeder Canal, Balochistan

  • Relevant Provincial Govts to work out proposals on implementation of projects

Gwadar Smart Port City Master Plan

  • LOE signed in August 2016

 Bao Steel Park, petrochemicals, stainless steel and other industries in Gwadar

  • Necessary approval process would be completed at the earliest for inclusion as new CPEC Project under Gwadar JWG

 Development of Gwadar University (Social Sector Development)

  • Chinese side will identify a leading Chinese university for collaboration with the University of Gwadar on marine Development) & maritime related subjects along with other disciplines

Punjab

Sahiwal Coal-fired Power Plant

  • Civil Work Completed
  • The first unit already inaugurated

Orange Line Train Project

  • The first train has arrived in Lahore

Rahimyar Khan Coal Power Project, Punjab

  • Feasibility in process

Zonergy 900MW Solar Park, Bahawalpur, Punjab

  • COD of 3 x 100 MW attained in August 2016

 Karot Hydropower Station, AJK & Punjab

  • . Financial Close (FC) 2017
  • . Construction in Progress.
  • . Commercial Operation Date (COD) 2020/2021

Matiari to Lahore Transmission line

  • A feasibility study completed.
  • TSA/IA initialed in December 2016
  • COD expected in 2018 / 2019
Interesting: CPEC a good deal or a bad deal?

Muzaffargarh Coal Power Project, Punjab

  • 25 KKH Phase II (Thakot -Havelian Section)
  • Contractor mobilized. Work commenced in September 2016
  • To be completed by March 2020

KPK

14 Suki Kinari Hydropower Station

  • Land acquisition award announced on 17th Nov 2016.
  • EPC Contractor mobilized to initiate construction activities
  • Commercial Operation Date (COD) 2021/2022.

Matiari to Faisalabad Transmission line

  • Feasibility study completed
  • COD expected in 2018 / 2019 TSA/IA initialed during 6th JCC

AJK

Kohala Hydel Project, AJK

  • Financial close planned in Dec 2017
  • Expected Commercial Operation Date (COD) 2023